Progress of IHT Report for 11 ULBs as on Monday, January 21, 2019

  

SNo.
(1)
Muncipality Name
(2)
No. of Households Verified by AE / AEE (Total)
(3)
No. of Households Verified by AE / AEE (Not Eligible)
(4)
No. of Households Verified by AE / AEE (Eligible)
(5)
No. of Households Taken up construction through Beneficiary
(6)
No. of Households Taken up construction through SLF
(7)
No. of Households Sanctioned by MC
(8)
No. of Households Open Site Photo-GEO Tagging Completed
(9)
No. of Households Photo-GEO Tagging Completed for First Payment
(10)
No. of Households First Payment Uploaded by MC using DSK
(11)
No. of Households IHHTs Completed
(12)
% of IHHTs Completed
(13)
No. of Households Second Payment Uploaded by MC using DSK
(14)
No. of Households Photo-GEO Tagging Completed for Third Payment
(15)
No. of Households final payment made
(16)
1 GVMC 12270 0 12270 10257 2013 12265 12261 12257 12250 12253 100% 12164 11897 11681
2 Guntur 10334 0 10334 0 10334 10329 10287 10287 10243 10155 98% 10074 10047 9949
3 Kakinada 4663 0 4663 2030 2633 4644 4309 4212 4206 4158 89% 4155 4120 4109
4 Kandukur 1706 0 1706 1381 325 1704 1701 1699 1690 1656 97% 1643 1562 1550
5 Kurnool 5506 0 5506 3132 2374 5503 5490 5486 5468 5447 99% 5384 5295 5055
6 Nellimarla 1034 0 1034 1004 30 1033 1033 1031 1027 983 95% 963 921 909
7 Ongole 9685 0 9685 1279 8406 9625 9373 9311 9227 9138 94% 9129 8803 8781
8 Rajam 2036 0 2036 2023 13 2035 1978 1952 1907 1831 90% 1803 1717 1686
9 Rajampet 334 0 334 55 279 334 333 330 330 324 97% 324 309 309
10 Srikakulam 2024 0 2024 1540 484 2024 2021 2010 2009 1987 98% 1983 1941 1928
11 Tirupathi 522 0 522 233 289 522 522 522 522 522 100% 522 522 522
  TOTAL 50114 0 50114 22934 27180 50018 49308 49097 48879 48454 97 48144 47134 46479