Progress of IHT Report as on Thursday, August 24, 2017

FROM DATE
 
TO DATE
 
SNo.
(1)
District Name
(2)
Total No. of applications received
(3)
Total No. of applications verified
(4)
No. of eligible applications
(5)
No. of Households Sanctioned by ULB
(6)
No. of Households Open Site Photo-GEO Tagging Completed
(7)
No. of Households Photo-GEO Tagging Completed for First Payment
(8)
No. of Households IHHTs Completed
(9)
% of IHHTs Completed
(10)
No. of Households final payment made
(11)
1 Ananthapur 31532 31532 28023 27765 27375 27196 26490 95 % 22417
2 Chittoor 10747 10747 7552 7468 7105 6899 6474 86 % 5626
3 East Godavari 16685 16685 15421 15383 14665 14210 13760 89 % 12880
4 Guntur 27936 27936 25975 25946 25416 25371 24583 95 % 22932
5 Krishna 15762 15762 14705 14649 14352 14284 13949 95 % 12995
6 Kurnool 24729 24729 22318 22278 21800 21565 20718 93 % 18823
7 Prakasam 16095 16095 15777 15748 15407 15302 14743 93 % 13678
8 SRI POTTI SRIRAMULU NELLORE 22338 22338 20930 20928 20553 20317 19620 94 % 17793
9 Srikakulam 9799 9799 9045 9030 8855 8686 8368 93 % 7596
10 Visakhapatnam 18971 18971 17130 16981 16744 16688 16309 95 % 15164
11 Vizianagaram 15966 15966 11555 11532 10839 10648 9823 85 % 8056
12 West Godavari 7801 7801 7181 7181 7177 7177 7143 99 % 6870
13 YSR 14265 14265 13243 13207 12600 12511 11587 87 % 9379
  TOTAL 208855 208096 202888 200854 193567 93% 174209